Project feature · Plattekloof, Cape Town
First-Floor Addition Plumbing: Plattekloof Rough-In Case Study
An upstairs bathroom starts with the plumbing behind the finishes. This residential first-floor addition is an awarded project in Plattekloof, Cape Town, currently at rough-in stage—not a completed installation showcase.
A project feature from The Cape Town Plumber (Pty) Ltd. Durbanville and the surrounding Northern Suburbs remain this website’s main service focus.

Project at a glance
Progress, not a completion claim.
- Location
- Plattekloof, Cape Town
- Project
- Residential first-floor addition
- Current stage
- Rough-in phase
- PIRB plumbing CoC
- Pending final inspection, testing and sign-off
Requested work, installed work and verified handover records are different. This feature keeps them separate.
Project background
A new bathroom above the existing home.
The project concerns a new first-floor residential addition. The owner confirms that the plumbing work has been won and that rough-in is the current stage. The original pricing request provides background for the intended bathroom and its water, drainage and hot-water connections.
Winning the work does not establish the final accepted specification. The request is useful context, but it cannot show which variations were agreed, what was ultimately installed or which tests have been completed. Those details need the final job records.
For fixture and alteration enquiries, see our bathroom and kitchen plumbing service. Its existing bath-cavity project remains a separate example.
Requested scope · not completed work
What the original work request describes.
The following is requested scope, not a checklist of completed work. Specific installed products, measurements and construction methods are deliberately not asserted.
Bathroom fixtures
The original request lists a bath, shower, WC (toilet) and wash hand basin. These describe the requested bathroom scope, not a verified final fixture schedule. The twin basins visible in the approved photograph are not evidence that the accepted scope was changed.
Water supply and waste
New hot- and cold-water distribution and waste pipework, with connections to existing water and drainage systems, are described in the request. The final routes, materials and connection methods have not been confirmed for this feature.
Geyser integration
The request includes a geyser and associated plumbing components. The installed capacity, model, component arrangement and discharge routes are not presented as verified specifications here.
Testing and handover
Testing, commissioning and a plumbing Certificate of Compliance on completion are included in the requested scope. They are future verification milestones, not reported results. The project CoC remains pending final inspection, testing and sign-off.
For help with an existing hot-water installation, read about geyser repairs and replacement.
The photographic record
From floor openings to the underground drain.
Sixteen progress photographs—from the upstairs rough-in to the exterior stack and the underground connection—and one approved bathroom-finish reference tell different parts of this project’s story. The progress images show exposed arrangements—not passed tests or completed work. People and identifying details have been removed from publication copies; the originals remain unchanged.
01 — Site access
An upstairs addition changes the access conversation.
What the photographs show
The supplied exterior photograph includes a geyser cylinder beside scaffolding. Only a small, privacy-safe equipment detail is shown here. It is not a record of how the equipment was lifted, who supervised access or whether an access arrangement was approved.
What to discuss on your addition
For a homeowner, the useful question is how equipment will reach the new floor or roof space without disrupting the existing home. Delivery routes, access constraints and coordination with other trades should be discussed before equipment arrives. Lifting and scaffolding decisions belong to competent site professionals, not to instructions inferred from a photograph.
Before the next stage: Ask who coordinates access and whether future maintenance equipment can reach the installation.

02 — Floor penetrations
Plan the route through the building—not just the fixture position.
What the photographs show
The photograph shows white pipework at an opening in an unfinished concrete floor. It makes the interface between plumbing and building work visible. It does not establish a core-drilling method, an engineered sleeve, reinforcement alterations or structural approval.
What to discuss on your addition
An upstairs bathroom needs routes for water arriving and wastewater leaving. Those routes may interact with floors, walls and the rooms below. Before any opening affecting structure is proposed, the plumber should coordinate with the appropriate building professionals. Pipe protection and the final treatment of an opening also need project-specific decisions; visible wrapping alone does not explain what protection has been specified.
Before the next stage: Confirm the proposed route and who approves any work affecting the existing structure before finishes conceal it.

03 — Wastewater routes
Three views of drainage before the finishes hide it.
What the photographs show
These photographs show branched wall-base pipework, a floor-level pipe connection and a square floor drain in exposed rubble. They document visible rough-in arrangements. They do not establish the final fixtures served, pipe diameters, venting, trap details or measured falls.
What to discuss on your addition
Waste pipes carry used water away from a basin, bath or shower. Their routes need to work with the final fixture positions and the connection to the existing drainage system. A fall is the slope of a drain; it cannot be measured reliably from an angled photograph. A shower drain also needs coordination with the finished floor and waterproofing work. Neither a drain sitting in the floor nor a neat-looking pipe run proves that those interfaces are complete or that drainage has been tested.
Before the next stage: Ask how the existing drain connection, final floor levels, access for maintenance and drainage testing will be confirmed.



04 — Concealed toilet plumbing
The cistern is visible now; future access still matters.
What the photographs show
The featured photograph above shows a concealed cistern recessed into unfinished masonry, with pipework below. It is evidence of a rough-in arrangement, not a completed toilet installation. The image does not prove anchoring details, final fixture compatibility or tested connections.
What to discuss on your addition
Concealed means that the cistern sits behind the finished wall rather than remaining fully exposed. Its installation needs to be coordinated with the selected toilet, the wall finish and the intended maintenance access. The final actuator or access arrangement should be checked against the selected product instructions. A homeowner should understand how serviceable parts will remain accessible; the photograph alone cannot answer that question.
Before the next stage: Confirm the final fixture selection, wall-finish allowance and intended service access before closure.
For broader fixture and alteration enquiries, see our bathroom and kitchen plumbing service.
A rough-in record worth keeping.
The cistern photograph is featured at the start of this page. Keep progress photos alongside the selected product information and the final job records. Each records something different; none replaces the others.
05 — Water supply & mixer connections
See where the water connections meet the wall.
What the photographs show
The photographs show a concealed shower mixer body and white supply pipes in wall channels. A wider view records the vertical routes; a close view records the exposed connection arrangement. These are useful complementary views, not separate claims that multiple installations were completed.
What to discuss on your addition
Supply pipework brings clean water to the fixtures. A mixer combines hot and cold water at the outlet. Its rough-in position needs to suit the chosen fittings and the thickness of the eventual wall finish. Product identity, pipe composition, jointing method, correct depth and test results cannot be established from these photographs. Before work is concealed, ask the responsible plumber what checks are appropriate, what has been recorded and whether any checks remain outstanding.
Before the next stage: Agree the selected mixer and finished-wall allowance, and ask for the relevant inspection and test records.



06 — Roof-space hot water
A visible geyser is not yet a verified hot-water system.
What the photographs show
The roof-space photograph shows a horizontal geyser, a dark tray, pipe connections and surrounding timber members. It does not verify the cylinder capacity or model, the adequacy of its support, the complete safety-component arrangement or where discharge pipes terminate.
What to discuss on your addition
The original request included a geyser and associated plumbing components. That request is not an as-built specification. When planning an upstairs bathroom, discuss hot-water demand, equipment access, the supporting arrangement and where any discharge will go. A tray is one visible component, not proof that the whole system has been checked. The responsible professionals need to confirm the actual installed arrangement and their respective responsibilities. Electrical certification is separate from plumbing certification.
Before the next stage: Confirm the equipment schedule, maintenance access, support and discharge arrangements, and the plumbing and electrical handover records.
For existing hot-water faults, explore geyser repairs and replacement.

07 — Exterior waste & stack
Getting wastewater from the new floor down the outside of the house.
What the photographs show
Three exterior photographs show scaffolding beside the double-storey wall, a white pipe run along the edge of a concrete cantilever with branch inlets, and a vertical pipe with angled offsets continuing upward past a window. They record visible routing on the outside of the building. They do not confirm pipe diameters, bracket spacing, measured falls or where the upper pipe terminates.
What to discuss on your addition
Wastewater from an upstairs bathroom has to reach the ground drainage somehow, and on many additions the route runs outside the building. Projections such as an overhang mean the route may need horizontal runs and offsets. Angled bends rather than sharp right angles are commonly used where pipes change direction, and soil stacks normally need venting so traps are not sucked dry. Which requirements apply, and how they are met, depends on the actual design and the applicable national building regulations; a photograph cannot confirm compliance.
Before the next stage: Ask how the external route will be supported, vented and protected, and how it will look once the house is painted.



08 — Underground connection
Where the new drainage joins the ground.
What the photographs show
The ground-level photographs show the white vertical pipe joining beige underground pipework through a curved bend, a pipe laid in an open trench along the wall beside an existing gully, and an angled junction with a capped, upward-facing pipe end. The trench is open in every image. Bedding, backfill, depth, fall and the final connection to the existing drainage are not evidenced.
What to discuss on your addition
Underground drainage is usually the hardest part to inspect later, so it is worth understanding before it is covered. Ask where the new run connects to the existing system, how access for future cleaning will be provided at bends and junctions, and how the pipe will be bedded and protected. Any drainage testing should happen before backfill hides the work. These are general questions; this page does not report a completed test or an approved connection.
Before the next stage: Confirm the connection point, cleaning access and testing before the trench is closed, and keep photographs of the open trench with your records.
For existing drain problems, see our sewer and drainage service.
For our parent company's dedicated breakdown of the exterior waste stack and underground connection, view The Cape Town Plumber: Plattekloof first-floor drainage project.



09 — Bathroom-finish reference
A finished-looking room is not a handover record.
This owner-approved photograph shows a bath, glass shower enclosure, toilet and twin basins. It is retained as a bathroom-finish reference, not proof that the first-floor addition is completed, commissioned or certified.
Nor does it confirm a final fixture schedule or a target specification. The current project status remains rough-in. The original request, progress photographs and any eventual handover records must be read separately.

Planning an upstairs bathroom
Three conversations to have before closing the walls.
These are general homeowner planning points, not an account of unverified methods used at this property.
- 01
Agree the fixture positions
For an upstairs bathroom, the position of each fixture influences where water must be supplied and where wastewater must leave. Discuss the chosen bath, shower, toilet and basin with the plumber before finishes conceal the connections. A photograph alone cannot establish the pipe routes or the final agreed fixture selection.
- 02
Coordinate routes with the building work
Supply pipes carry clean water to fixtures; waste pipes carry used water away. An upper-floor addition needs both considered alongside the existing building. Any proposed openings or changes affecting structure should be agreed with the appropriate building professionals. This is planning guidance, not a claim that a particular opening, stack size or structural method was used on this project.
- 03
Keep the hot-water system in the conversation
Discuss where hot water will come from, which fixtures it will serve, and how the system can be accessed for maintenance. Geyser plumbing and electrical work have different responsibilities. Confirm the actual equipment and arrangements with the project team rather than treating a requested specification as an installed one.
Planning an addition in Durbanville?
Tell us the intended fixtures and the stage of your building work. We can discuss the next assessment step; the work and quotation depend on your property.
10 — Testing & documentation
The handover evidence is still to come.
01 · Confirm what was actually installed
Reconcile the accepted scope and any variations with the fixtures, pipework and hot-water equipment actually installed. The original pricing request is background, not the final record.
02 · Record inspection and testing
The responsible plumber must confirm the applicable checks and their results. Supply checks, drainage checks and commissioning records answer different questions; no passed results are reported for this project.
03 · Confirm each document separately
The PIRB plumbing CoC remains pending final inspection, testing and sign-off. Any applicable City of Cape Town process and geyser electrical documentation must be considered separately, with their own confirmed status.
The owner confirms that the PIRB plumbing CoC is pending final inspection, testing and sign-off. No completed pressure test, commissioning result or issued certificate is reported here. A photograph cannot establish any of these outcomes.
A PIRB plumbing Certificate of Compliance is distinct from any City of Cape Town notification, approval or inspection steps that apply. Neither municipal approval nor completed municipal paperwork is claimed for this project. Electrical certification for a geyser is also separate from plumbing certification.
The project account can be updated when the final installed scope, test records, commissioning and document status are confirmed. Read our plumbing compliance and CoC information for the broader inspection-first approach.
11 — Homeowner questions
First-floor addition plumbing, explained.
What does rough-in plumbing mean?
Rough-in, also called first fix, is the stage in which plumbing routes and connection points are prepared before the final connections and finishes are fully resolved. The exact work varies by project. For this first-floor addition, the owner confirms rough-in as the current stage; this page does not claim that every requested component has been installed or tested.
Is this first-floor addition plumbing project completed?
No. The owner confirms that the project is in the rough-in phase. The approved photograph shows bathroom finishes, but it is not a completion record for the addition plumbing. Final installed specifications, commissioning results and handover records are not claimed on this page.
Has a PIRB plumbing CoC been issued for this project?
No issued CoC is claimed. The owner confirms that the PIRB plumbing CoC is pending final inspection, testing and sign-off. A plumbing CoC and any applicable City of Cape Town approval or inspection process are distinct. This page does not report municipal approval or completed inspection paperwork.
What should I discuss before adding a bathroom upstairs?
Start with the fixtures, their intended positions, existing water and drainage connections, hot-water requirements and the sequence of the building work. Ask what the quotation includes and which tests and documents will be provided. The plumber and relevant building professionals need to assess the actual property before project-specific methods or costs can be confirmed.
Can a photograph prove that upstairs plumbing is compliant?
No. A photograph can show an exposed arrangement or a visible component, but it cannot prove hidden connections, measured pipe falls, structural approval, passed tests or certification. Use photographs alongside confirmed job records, not instead of them. For this feature, the supplied photographs are paired with descriptions of what is visible and questions a homeowner can raise. The final installed specification and handover results remain unverified. Any applicable municipal process must also be checked separately from the PIRB plumbing CoC.
Why does an upstairs bathroom need pipework on the outside wall?
Wastewater from a new upper floor must travel down to the ground drainage. Where routing inside the existing house is impractical, the waste and stack pipework is often run on the exterior wall. In this project, photographs show a pipe run along a concrete cantilever and a vertical pipe with angled offsets continuing upward. Pipe sizes, supports, venting and falls are not confirmed by those images. The right route depends on the building, the fixture positions and the existing drainage, so it should be agreed with the plumber and the relevant building professionals before work starts. Ask how the exterior pipes will be supported and finished, and how they will be inspected and tested before the job is signed off.
How does a roof-space geyser affect an upstairs bathroom addition?
It brings hot-water demand, access, support and discharge arrangements into the planning conversation. The appropriate system depends on the property and selected fixtures, not on the appearance of a cylinder in a photograph. Here, a roof-space geyser and tray are visible, while capacity, support design, discharge destination and commissioning results are not verified. Ask the responsible professionals to confirm the actual equipment and arrangements, maintenance access and the relevant records. Plumbing and electrical certification have distinct responsibilities.
Looking for help closer to home? Explore Durbanville plumbing services and practical guides.